Due to an unforeseen issue, Inframark will be rescheduling the Air Scouring work for Meadow Place I. Greenway Village VI will proceed as scheduled. Please see below updated schedule for District website:

  • 2-3 days prior, Inframark will conduct a valve survey and ensure that all field aspects are lined up to successfully perform the project.
  • Friday, July 23, 2021 all effected homes will be door-tagged with the attached hanger.
  • Monday, July 26, 2021 Greenway Village VI will be air scoured. Residents in the area will experience a service interruption from 9:00 AM-2:00 PM.
  • Meadow Place I pending reschedule.

All of the same protocols will be followed prior to performing work in Meadow Place I. Inframark will provide further updates as we solidify the new date.